Past Projects Using MUSTY2009

MUSTY2009 has been successfully deployed across major national and international oil spill responses, demonstrating its effectiveness in large-scale environmental remediation, shoreline recovery, and hazardous waste management.

Ramlet Al Baida Beach – Lebanon

Client: Government of Lebanon & United Nations
Period: January 2008 – November 2008
Scope: Large-scale shoreline clean-up, decontamination, and removal of spilled fuel oil following Israeli rocket fire that damaged a major fuel oil pipeline. MUSTY2009 was used extensively to support the restoration of the contaminated coastline.

Holcim Chekka Beach – Lebanon

Client: Holcim (Liban) S.A.L.
Period: December 2008 – March 2009
Scope: Clean-up, decontamination, and removal of fuel oil following a pipeline spill impacting the Chekka beachfront.

Holcim Chekka Beach – Contract #0201/HOL/SP

Client: Holcim (Liban) S.A.L.
Period: March 2009 – June 2010
Scope: Extended remediation works involving ongoing shoreline clean-up, decontamination, and safe removal of fuel oil contaminants caused by pipeline leakage.

Zahrani Refinery Oil Spill Waste Management – UNDP (Amendment No.1)

Client: United Nations Development Programme (UNDP)
Period: July 2009 – October 2010
Scope: Continued environmental management of stored oil spill waste, expanding the original project to ensure long-term compliance and ecological protection.

Zahrani Refinery Oil Spill Waste Management – UNDP

Client: United Nations Development Programme (UNDP)
Contract: UNDP Contract No. 08/55
Period: February 2009 – June 2010
Scope: Environmentally sound management, treatment, and handling of stored oil spill waste at the Zahrani Refinery using MUSTY2009 technologies.

Deepwater Horizon Oil Spill – USA

Client: BP
Period: May 2010 – July 2010
Scope: Consulting services supporting oil spill response efforts following the Deepwater Horizon disaster.